Next Step Upon the successful completion of system pressure testing, the system is ready for connection to be Board's distribution system. to get the "Connection Form" (LAK/NM/R007). Connections can be performed by the main layer (supervised by KWB staff) or by the Board's New Mains Section. Flushing and sampling will be done by KWB staff.
Final Step To get the Final Inspection Form (LAK/NM/R016). The final inspection can only be made after the flushing bill and the connection bill have been paid.
Please get the "Handing Over Certificate" Form (LAK/NM/R013) from New Mains Section.